5. Chapter Five: Project Risk Management
Downloadable file:
https://drive.google.com/file/d/1QRlRDSc2eCegvOSX5zRRRRcfU0rB9k8p/view?usp=sharing
YouTube Video
Class Day 22:
https://www.youtube.com/watch?v=qEocMnLf64E&list=PLGYMTr4BT9IxTt8jLIGOOzy0mjtXLHeMy&index=25
Class Day 23:
https://www.youtube.com/watch?v=Je1FEBh3rps&list=PLGYMTr4BT9IxTt8jLIGOOzy0mjtXLHeMy&index=26
Class Day 24:
https://www.youtube.com/watch?v=Z_Ztek_XR10&list=PLGYMTr4BT9IxTt8jLIGOOzy0mjtXLHeMy&index=27
CHAPTER 5- PROJECT RISK MANAGEMENT
5.1 Introduction to Project Risk
When
our World was created, nobody remembered to include Certainty
-
PETTER BERNSTEIN
Every project is risky, meaning there is a
chance things won't turn out exactly as planned. Project outcomes are determined
by many things, some that are unpredictable and over which project managers
have little control. Risk level is associated with the certainty level about
technical, schedule and cost outcomes. High certainty outcomes have low-risk;
low- certainty outcomes have high risks. Certainty derives from knowledge and
experience gained in prior projects, as well as from management's ability to
control project outcomes and respond to emerging problems.
In general, risk is a function of uniqueness of a project and the experience of the project team.
Risk = f
(uniqueness, experience of project team)
Project Risk
Project risk is an uncertain event or condition that, if it
occurs, has a positive or negative effect on a project objective. A risk has a
cause and, if it occurs, an impact. For example, the cause may be requiring a
permit or having limited personnel assigned to the project. The risk event is
that the permit may take longer than planned or the personnel may not be
adequate for the task. Project risk includes both threats to the project’s
objectives and opportunities to improve on those objectives.
The notion of project risk involves two
concepts:
- The likelihood that some problematical
event will occur.
- The impact of the event if it does occur.
Risk is also the joint function of:
Risk – f (likelihood, impact)
A project will be ordinarily considered risky
whenever at least one factor – either the likelihood or the impact- is large.
For example, a project will be considered risky where the potential impact is
human fatality or massive financial loss even when the likelihood of either is
small.
· Risk should be related to reward.
· Risks accepted should be in balance with the reward that may be gained by taking the risk.
· For example, a fast-track schedule is a risk taken to achieve the benefit of a shortened schedule.
Broadly, there are five
main categories of risk types associated with project management.
1.
External Risks
External events are mainly
outside the control of the project manager and, in most cases, the
organization. Examples include:
·
Marketplace
developments—rapid developments can cause an abrupt change of direction
·
Market
risks include competition, foreign exchange, commodity markets, and
interest rate risk, as well as liquidity and credit risks
·
Government
regulatory changes
·
Industry-specific
procedures—new standards, issues
·
Legal
issues-disputes, lawsuits, and court orders
·
Change-driven
factors-new products, services, changes in market
·
Corporate
strategy and priority changes
·
Disasters
such as fire, flood, earthquake, or other natural disaster
·
Risks
associated with labor strikes; and civil unrest
·
Risk
Associated with Loss of power, heating, or ventilation; air conditioning
failure
·
Communications
systems and security sensor failures
·
Emergency
destruction of communications
Most of these risks are
very difficult to control at the project manager level but can be identified
and, therefore, managed. This means that senior management must be involved in
the risk management process and have input into risk control issues.
2.
Cost Risks
Many of these types of
risks are directly or indirectly under the project manager's control or within
his or her area of influence. Cost risk, typically escalation of project costs
due to poor cost estimating accuracy and scope creep.
Examples of cost risks include those arising
from:
·
Cost
overruns by project teams or subcontractors, vendors, and consultants
·
Scope
creep, expansion, and change that has not been managed
·
Poor
estimating or errors that result in unforeseen costs
·
Overrun
of budget and schedule
3.
Schedule Risks
Schedule risks can cause
project failure by missing or delaying a market opportunity for a product or
service. Schedule risk is the risk that activities will take longer than
expected. Slippages in schedule typically increase costs and, also, delay the
receipt of project benefits, with a possible loss of competitive advantage. Such
risks are caused by:
·
Inaccurate
estimating, resulting in errors
·
Increased
effort to solve technical, operational, and external problems
·
Resource
shortfalls, including staffing delays, insufficient resources, and unrealistic
expectations of assigned resources
·
Unplanned
resource assignment—loss of staff to other, higher-priority projects
4. Technology Risks
Technology risks can result
from a wide variety of circumstances. The result is failure to meet systems'
target functionality or performance expectations. Performance risk is the risk
that the project will fail to produce results consistent with project
specifications. Typical examples are:
·
Problems
with immature technology
·
Use
of the wrong tools
·
Software
that is untested or fails to work properly
·
Requirement
changes with no change management
·
Failure
to understand or account for product complexity
·
Integration
problems
·
Poor
Software/hardware performance issues—poor response times, bugs, errors
5. Operational Risks
Operational risks are
characterized by an inability to implement large-scale change effectively. Such
risks can result in failure to realize the intended or expected benefits of the
project. Typical causes are:
·
Inadequate
resolution of priorities or conflicts
·
Failure
to designate authority to key people
·
Insufficient
communication or lack of communication plan
·
Size
of transaction volumes—too great or too small
·
Rollout
and implementation risks—too much, too soon
·
Poor
implementation, procurement etc
5.3 Analysis of Major Sources of Risk
Any factor with an uncertain probability of occurring that can influence the outcome of a project is considered as risk source or risk hazard. The most difficult part of risk identification is discovering things we don’t already know! Project risk’s source can be classified as internal risks and external risk
1.
Internal
Sources of risk:
Internal risks originate
inside the project and project managers and stakeholders usually have a measure
of control over these. Two main categories of internal risk source are market
risk and technical risk
a.
Market
risk
Market risk is the risk
of not fulfilling either market needs or the requirements of particular
customers. The sources of market risk include
·
Incompletely / in adequately defined
market or customer needs
·
Failure to identify changing needs
·
Failure to identify newly introduce
products by competitors
Technical risk is the
risk of not meeting time, cost or performance requirements due to technical
problems with the end-item or project activities. These risks are high in
projects involving activities that are unfamiliar or require new ways of
integration and especially high in projects with untried technical
applications.
One approach to
expressing technical risk is to rate the risk of the project end item or
primary process as being high, medium or low according to the following
features:
Maturity - An end item or
process that is pre- existing, installed and operational or based on experience
and pre- existing knowledge entails less risk than in the early stage of
development or new
Complexity - An end item or
process with numerous interrelated steps or components is more risky than one
with few steps and components having simple relationship
Quality - An end-item
or process that is known to be completely producible, reliable or testable is
less risky than one that has not yet been produced or has low reliability or
testability
Concurrency
or Dependency - In
general risk increases the more that activities overlap one another.
Sequential, dependent activities with no overlap are much less risky than those
with much overlap
2.
External Sources of risk:
External risk include
only risk that stem from sources outside the project. Project managers and
stakeholders usually have little or no control over these. External risk
hazards include changes in:
- Market conditions
- Competitor’s actions
- Government regulations
- Interest rates
- Decisions made by senior management /
customers regarding project priorities, staffing or budgets
- Customer needs and behavior
- Weather (adverse)
- Labor availability (Strikes / Walkouts)
- Material / labor resources (Shortages) etc.
Risk Management
Risk management is the systematic application of the risk management processes on a project. The processes consist of risk management planning, identification, analysis, responding, and monitoring & control.
The objective of risk management is to maximize the probability and impact of positive events and minimize the probability and consequences of events adverse to project objectives.
- Ensure that the risk management effort is proportionate to both the risk and importance of the project to the organization.
- Provide enough resources for risk management activities.
- Establish basis for evaluating risk.
Risk Management Process/ Cycle
The processes of risk management are updated throughout the project life. It involves following steps:
1.Risk Management Planning - Deciding how to approach and plan the risk management activities for a project.
2. Risk Identification - Determining which risks might affect the project and documenting their characteristics.
3. Qualitative Risk Analysis - Prioritizing risk by their effects on project objectives through assessment of their probability, impact, and the combination of both
4. Quantitative Risk Analysis - Quantitatively analyzing the effect of identified risks on project objectives
5. Risk Response Planning - Developing options and ways to enhance opportunities and to reduce threats to the project’s objectives
6. Risk Monitoring and Control - Monitoring identified and residual risks, identifying new risks, executing risk response plans and evaluating their effectiveness throughout the project life cycle
1. Risk Management Planning
Risk management planning is the process of deciding how to approach and perform the risk management activities for a project.
- Ensure that the risk management effort is proportionate to both the risk and importance of the project to the organization.
- Provide enough resources for risk management activities.
- Establish basis for evaluating risk.
Risk management planning is the first step of risk management process in a project. The documents related to project environment factors, project scope, project management plan required for the risk management plan are required for the risk management planning. Stakeholder’s risk tolerance is prime matter. After having these documents a risk planning meeting is carried out on the behalf of PM and all other stakeholders to prepare the risk management plan.
Risk Management Plan (RMP)
It is the document prepared after the risk management planning meetings which shows/describes the way, mechanism and methods of performing risk identification, risk analysis, response planning and risk Monitoring and controlling mechanism. RMP includes:
- Methodology
- Roles and responsibilities
- Timing
- Budgeting
- Risk categories and Risk Break down structure
- Risk Probability and impact
- Revised stakeholder’s risk tolerances
- Reporting format
- Tracking
2. Risk Identification
The process of identifying the risk with the involvement of various participants of project is known as risk identification. The participants can be project team, risk management team, subject matter experts, customers, end users, outside experts etc. The various sources are analyzed in order to identify the associated risk with the project through risk identification. Risk management plan and risk break down structures are required for the risk identification process.
Objective of risk identification
· To determine the risks that may affect the project
- To document their characteristics
Risk management plan and risk break down structures are required for the risk identification process. Review of documents related to project files, checklists information gathering technique like brainstorming, Delphi technique, interviewing, SWOT analysis, assumption analysis and diagramming techniques are used for risk identification process. Risk register is prepared after completion of the risk identification process.
Risk Register (RR)
Risk register is a record to document the results of the risk management process. It contains the following information.
- ·
List of identified risks with description
- ·
List of potential responses
- ·
Root causes of risk
- ·
Updated risk categories
3. Qualitative Risk Analysis
Qualitative risk analysis is the application of methods for ranking the identified risks according to their potential effect on project objectives. This process prioritizes risks according to their potential effect on project objectives.
Qualitative risk analysis is one way of determining the importance of addressing specific risks and guides risk response measures. The RMP and RR is required for the qualitative risk analysis process. The risk probability and impact assessment is carried out. The risk probability and impact are rated and presented in matrix known as probability-impact matrix. The risk register will be updated after completing the qualitative risk analysis. Updates of risk categories according to the impact scale and urgency is done.
4. Quantitative Risk Analysis
Quantitative risk analysis analyzes numerically the effect a project risk has on a project objective. The process generally follows qualitative analysis and utilizes techniques such as Monte Carlo simulation and decision analysis to:
Source: PMBOOK 2000
5. Risk Response Planning
Risk response planning addresses the matter of how to deal with risk. Risk response must be proportional to the severity of the risk, cost effective, timely, realistic and accepted as well as owned by all concerned parties of the risk management.
Objective of risk response planning
·
Develop
options and determine actions to enhance opportunities and minimize threats to
project objectives.
Assign responsibility to individuals or parties for each risk response
Various data and documents are required for the risk response planning like RMP, RR, Risk thresholds, Risk owners, risk priorities list etc. risk response can be carried out by using following two strategies.
- a.
Strategies for negative risk (threats)
- b.
Strategies for positive risk (opportunity)
Risk avoidance is the process to avoid the risk by changing the project plan to eliminate the risk. It can also be carried out by relaxing the relevant objectives by extending the schedule or increasing the cost in project. All risk cannot be avoided, but some may. Examples of risk avoidance are: add resources, improve communication, avoid unfamiliar sub-contractor, adopt familiar approach etc.
2. Risk Transfer
Transfer the risk to the third party who will carry the risk impact and ownership of the response. Risk transfer is most effective in dealing with financial risk exposure. The transfer of risk liability to sub-contractor, the use of risk insurance and payment of risk premium, performance bonds, warranties etc. are examples of risk transfer.
3. Risk Mitigation
Risk mitigation aims at reducing the probability and/or impact of a risk to within an acceptable threshold. The probability/Impact should be mitigated before the risk takes place. Thus avoiding dealing with the consequences after the risk had occurred. Mitigation costs should be appropriate given the likely impact and probability of the risk. Examples of risk mitigation are: adopting less complex process, adding resources to the schedule, conducting more engineering tests and inspections etc.
4. Risk Acceptance
Acceptance indicates a decision not to make any changes to the project plan to deal with a risk or that a suitable response strategy cannot be identified. This strategy can be used for both negative and positive risks
There are two types of acceptance:
- Active acceptance: may include developing a contingency plan to execute should a risk occur.
- Passive acceptance: requires no action. The project team will deal with the risk as it occurs.
Contingency Plan
A contingency plan is developed in advance to respond to risks that arise during the project. Planning would reduce the cost of an action the risk occurs. Risk triggers, such as missing intermediate milestones, should be defined and tracked. The most usual risk acceptance response is to establish a contingency allowance, or reserve, including amounts of time, money or resources to account for known risks. The allowance should be determined by the impacts, computed at an acceptable level of risk exposure, for the risks that have been accepted.
Positive risks are response by either of the following techniques
1. Exploit the opportunity
Ensure that the risk event happens by eliminating the uncertainty. to take advantage of the opportunity. Examples: assign qualified personnel, select an appropriate project delivery, and provide better quality.
2. Share the risk
Allocate ownership to a third party who has a better chance of achieving the required results. Examples: joint ventures, partnerships, rewards.
3. Enhance
Increase the likelihood of occurrence or the impact of the event. Improve chances for the event to happen so the opportunity becomes more certain. Consider how the impact can be increased and choose a course of action that in the increased impact
4. Accept the risk
Active acceptance: may include developing a contingency plan to execute should a risk occur. Passive acceptance: requires no action. The project team will deal with the risk as it occurs. Risk response planning will update the risk register. The risk register is updated to reflect the results of the response planning process. Level of detail of documenting a risk should be appropriate to the ranking of the risk (high risks in detail, low risks by listing). Items in the risk register are:
- · Identified risks
- · Risk owners
- · Results from risk analysis
- · Budget and schedule activities
- · Response strategies
- · Contingency plans
- · Fallback risks
- · Residual risks
- · Secondary risks
Similarly project management plan will be updated and contractual agreements are set up for the risk response.
6. Risk Monitoring and Controlling
Risk monitoring and control is required in order to:
- · Ensure the execution of the risk plans and evaluate their effectiveness in reducing risk.
- · Keep track of the identified risks, including the watch list.
- · Monitor trigger conditions for contingencies
- · Monitor residual risks and identify new risks arising during project execution.
- · Update the organizational process assets.
Purpose of risk monitoring
The purpose is to determine if:
- · Risk responses have been implemented as planned.
- · Risk response actions are as effective as expected or if new responses should be developed.
- · Project assumptions are still valid.
- · Risk exposure has changed from its prior state, with analysis of trends.
- · A risk trigger has occurred.
- · Proper policies and procedures are followed.
- · New risks have occurred that were not previously identified.
Risk monitoring needs a data like RMP, updated RR, change request if any from the response and performance indicators. Risk monitoring and control is carried out by following methods:
a. Risk Reassessment
Project risk reviews at all team meetings. Major reviews at major milestones
Risk ratings and prioritization may change during the life of the project. Changes may require additional qualitative or quantitative risk analysis.
b. Risk audits
Examine and document the effectiveness of the risk response planning in controlling risk and the effectiveness of the risk owner.
c. Variance and Trend Analysis
Used for monitoring overall project cost & Schedule performance against a baseline plan. Significant deviations indicate that updated risk identification and analysis should be performed.
d. Reserve Analysis
As execution progresses, some risk events may happen with positive or negative impact on cost or schedule contingency reserves. Reserve analysis compares available reserves with amount of risk remaining at the time and determines whether reserves are sufficient
e. Status meetings
Risk management can be addressed regularly by including the subject in project meetings.
Risk M&C helps to update the RR, it suggest the corrective and preventive actions along with change request. More over project management plan will be finally updated.
Table: Comparison of Risk management Guidelines among various agencies
References
1. R.Panneerselvam and P. Senthil kumar “ Project Management” Eastern Economy Edition, PHI Learning Private Limited, New-Delhi, India
2. Monisha Chattopadhya “Project Management”, New Edition, Neeraj Publications Delhi, India
3. Dr. H.L. Kaila “Organizational Behavior and HRM” Third Edition, AITBS Publishers, India
4. Dr. Govinda Ram Agrawal “Project Management in Nepal” New Edition, M.K Publishers and Distributors.
5. A text book of Project Engineering (revised edition) by Santosh Kumar Shrestha & Ishwor Adhikari
6. Acharya Kedar Prasad “Project Management”, Ashmita Books Publishers & Distributors (P) Ltd.
7. Acharya Bhawani Shankar “Organizational Behavior”, Ashmita Books Publishers & Distributors (P) Ltd
8. Dr. Govinda Ram Agrawal “ Dynamics of Human Resource management in Nepal” New Edition, M.K Publishers and Distributors
9. Subash Kumar Bhattarai, Santosh Kumar Shrestha, & RK Shrestha ''A Text Book of Construction management" Heritage Publishers and Distributors Pvt. Ltd., Bhotahity, Kathmandu.
10. A manual on fundamentals of project management (by Er. Harimohan Shrestha), manual note for MSc CM Nepal Engineering College
12. Project Management Institute of America (PMI, USA)
13. Other related websites and freely available materials
Comments
Post a Comment